Project: gas transition to Aftab town of Imam Khomeini holly shrine
Employer: Sahand Plateau Line
Project description: transmission of steel casing pipe with diameter of 12 inch and 80 meter long to Aftab town under Tehran-Qom highway
This project was done fully automatic without any need for hand drilling with pipe jacking method using machine HS700B and it was delivered to employer at predicted time in September 2015
|